● (74) is primarily concerned with defining and controlling what is and is not included in

题目

● (74) is primarily concerned with defining and controlling what is and is not included in the project.

(74)

A. Project Time Management

B. Project Cost Management

C. Project Scope management

D. Project Communications Management

参考答案
正确答案:C