Each box is an activity; the number it contains is the duration of the activity in days. T

题目

Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75)

A.16days

B.14days

C.19days

D.20days

参考答案
正确答案:C
解析:关键路径为最长时间的线路,3+6+7+1+2=19。