______is primarily concerned with defining and controlling what is and is not included in
______is primarily concerned with defining and controlling what is and is not included in the project.
A.Project Time Management
B.Project Cost Management
C.Project Scope management
D.Project Communications Management
解析:项目范围管理是项目管理(包括时间、成本、沟通)的基础。
项目范围管理是最先定义和决定项目中包含哪些内容和确定边界的。
选项A是项目时间管理,选项B是项目成本管理,选项C是项目范围管理,选项D是项目沟通管理,因此应选择C。
A snake is a strange.It walks on its ribs and it 英语 2020-05-13 …
A a snake is a strange animal. it walks on its ri 英语 2020-05-13 …
He is not my close friend and not one who I can _ 英语 2020-05-13 …
don"t punish a dog one time and not the next time 英语 2020-05-14 …
Once in a while it"s okay just to take out one ea 英语 2020-05-14 …
请问:really not and not really 有什么区别? 英语 2020-05-14 …
哪篇英语文章开头是why did the chicken cross the road?Answe 英语 2020-05-14 …
Is Millie really a girl out of fashion and not { 英语 2020-05-14 …
英语翻译From the time we were babies we have been tau 英语 2020-05-15 …
连词成句sister,brother,my,and,not,do,a,have,watch 英语 2020-05-16 …