Estimating schedule activity costs involves developing an (74) of the cost of the resource

题目

Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.

A.accuracy

B.approximation

C.specification

D.summary

参考答案
正确答案:B