The difference value between Budgeted Cost for work Performed and Actual Cost for Work Per

题目

The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).

A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index

参考答案
正确答案:A