( )is the approved version of the time-phased project budget,excluding any management rese

题目

( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

A.The control accounts

B.Funding requirement

C.The cost estimates

D.The cost baseline

参考答案
正确答案:D