You are a project manager for a small project. Your project was budgeted for ¥500,000 over

题目

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perio.As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

A.Ahead of schedule

B.Behind schedule

C.On schedule

D.Having not enough information provided

参考答案
正确答案:B
你是一个项目经理。你目前负责的项目预算是50万元,工期是6周。到目前为止,你已经花费了26万工程款,完成了预算中28万的工作量。根据你之前制定的进度计划,到目前为止,你应该花费30万元工程款。根据这些描述,你的工程目前____________。