Project manager believes that modifying the project scope may provide added value for the

题目

Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).

A.change the scope baseline

B.contact the customer to determine if the change adds value

C.call a meeting of the change control board

D.change the project’s objectives

参考答案
正确答案:C
项目经理相信调整范围能为客户增加收益,项目经理应该(73)。A:改变范围基线、B:联系客户确定变更是否增加收益、C:召开变更控制委员会会议、D:改变项目目标。