Since risk is associated with most projects,the best course of action is to ( )A.cover all

题目

Since risk is associated with most projects,the best course of action is to ( )

A.cover all project risks by buying appropriate insurance

B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner

C.avoid project with clear and present risk

D.identify various risks and implement actions to mitigate their potential impact

参考答案
正确答案:D
识别所有风险,潜在应对措施。