早教吧 育儿知识 作业答案 考试题库 百科 知识分享
早教吧考试题库频道 --> 财会类考试 -->ACCA/CAT -->

(b) Analyse how effective project management could have further improved both the process

题目

(b) Analyse how effective project management could have further improved both the process and the outcomes

of the website re-design project. (10 marks)

参考答案
正确答案:

(b) Effective project management could have improved the conduct of the website re-design project in the following ways:
Detailed planning
During the delivery of the project the lack of a formal detailed plan means that there is no baseline for review and control.
The absence of monitoring progress against that plan is also very evident. The meetings are events where, although progress
appears to have been made, it is unclear how much progress has been made towards the delivery of the final re-designed
website. Effective project management would have mandated the production of a detailed plan. There is no mention of a
project plan, a critical path analysis, a Gantt chart or supporting project management software.
Effective monitoring and control
The board were not kept up to date about progress and were only alerted to potential issue when the finance director became
concerned about spiralling costs. This is a failure of monitoring and control, aggravated by the fact that there is no project
plan to monitor against. Effective project management would have required formal progress to the sponsor (in this case the
board). Such monitoring should lead to project control, where suggested actions are considered and implemented to deal with
project slippage. The planning, monitoring and controlling aspects of project management are completely absent from the
scenario and so none of the usual project management monitoring and reporting structures were in place to alert the board.
Mandating of substitutes
Initial progress is hampered by the absence of key personnel at meetings 3 and 4 and the inappropriate sign-off by the RP
(already discussed above) of the technical design. The requirement for the TD to produce a technical report also slows
progress. These problems could have been addressed by ensuring that substitutes were available for these meetings who
understood their role and the scope of their authority. Effective project management would have ensured that progress would
not have been delayed by the absence of key personnel from the progress meetings.
Standards for cost-benefit analysis
The cost-benefit analysis provided by the MM is flawed in two ways. Firstly, the assumptions underpinning the benefits are
not explained. There is no supporting documentation and it appears, at face value, that year four and five benefits have been
greatly inflated to justify the project. Secondly, it would be usual to discount future costs and benefits using an agreed discount
rate. This has not been done, so the time value of money has not been taken into account. Effective project management
would have defined standards for the cost-benefit analysis based on accepted practice.
Estimating, risks and quality
The reaction of the board to the cost-benefit analysis also appears unrealistic. They appear to have suggested a budget and
a timescale which does not take into account the complexity of the remaining work or the resources available to undertake
it. The estimating part of the project management framework appears to be lacking. It is clear at the final meeting that the
website will not be ready for launch. However, the MM decides to take the risk and achieve the imposed deadline and take
a chance on the quality of the software. This decision is made against the advice of his TD and without any information about
the quality of the software. Effective project management would have mandated a framework for considering the balance
between risk and quality.

The MM does not inform. the board of the TD’s advice. The MM, like many project managers (because the MM now appears
to have adopted this role) finds it politically more acceptable to deliver a poor quality product on time than a better quality
product late. Unfortunately the product quality is so poor that the decision proves to be the wrong one and the removal of the
software (and the resignation of the MM) ends the project scenario.