● Project manager believes that modifying the project scope may provide added value for th

题目

● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

(73) A. change the scope baseline

B. contact the customer to determine if the change adds value

C. call a meeting of the change control board

D. change the project' s objectives

参考答案
正确答案:B