早教吧 育儿知识 作业答案 考试题库 百科 知识分享
早教吧考试题库频道 --> 计算机类考试 -->软考中级 -->

● Project manager believes that modifying the project scope may provide added value for th

题目

● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .

(73) A. change the scope baseline

B. contact the customer to determine if the change adds value

C. call a meeting of the change control board

D. change the project' s objectives

参考答案
正确答案:B
看了● Project manag...的网友还看了以下: