The project()is a key input to quality planning since it documents major project deliverab

题目

The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

A.work performance information

B.scope statement

C.change requests

D.process analysis

参考答案
正确答案:B