Project Time Management includes the processes required to manage timely completion of the

题目

Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities

参考答案
正确答案:A
解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。