The customer asks your project to be completed 6 months earlier than planned.You think thi

题目

The customer asks your project to be completed 6 months earlier than planned.You think this target can be reached by-overlapping project activities. This approach is known as ().

A.balance engineering

B.fast-tracking

C.leveling

D.crashing

参考答案
正确答案:B