Many useful tools techniques are used in developing schedule. ( )s a schedule network anal

题目

Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

参考答案
正确答案:B