Schedule development can require the review and revision of duration estimates and resourc

题目

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74) that can serve as a baseline to track progress.

A.scope statement

B.activity list

C.project charter

D.project schedule

参考答案
正确答案:D