试题(73)Tool for defining activities is(73).(73)A.Dependency Determination B.Precedence Di
试题(73)
Tool for defining activities is(73).
(73)
A.Dependency Determination
B.Precedence Diagramming method
C.Rolling Wave Planning
D.Schedule network Templates
试题(73)分析
用于定义活动的工具/方法是?
选项A是依赖关系确定法,选项B是前紧关系绘图法,选项C是滚动式规划,选项D是进度网络模板。其中A、B、D是活动排序的方法和工具。
因此,正确答案是C。
参考答案
(73)C
kinds of activities do Chinese people like for re 英语 2020-05-16 …
It's a good time for outdoor activities in spring 其他 2020-05-16 …
这个句子有点长,The clause should be sufficiently vague a 英语 2020-05-16 …
they ,with,ask,for,me,them,to,stay,a,week连词成句2、lu 英语 2020-05-16 …
the engineer are so busy that they have zero time 学历类考试 2020-05-24 …
● (73)is the application of planned, systematic qu 计算机类考试 2020-05-26 …
● __(73)__ are the four major activities of softwa 计算机类考试 2020-05-26 …
试题(73)Tool for defining activities is(73).(73)A.De 计算机类考试 2020-05-26 …
A critical path for a project is the series of act 计算机类考试 2020-05-26 …
Tool for defining activities is( ).A.Dependency De 计算机类考试 2020-05-26 …