Tool for defining activities is( ).A.Dependency Determination B.Precedence Diagramming

题目

Tool for defining activities is( ).

A.Dependency Determination

B.Precedence Diagramming method

C.Rolling Wave Planning

D.Schedule network Templates

参考答案
正确答案:C
看了Tool for defini...的网友还看了以下:

Learning english,make people`s life more interest 英语 2020-05-16 …

● One tool that is useful during both analysis and 计算机类考试 2020-05-26 …

● (74) is primarily concerned with defining and co 计算机类考试 2020-05-26 …

● A work breakdown structure (WBS) is a tool used 计算机类考试 2020-05-26 …

试题(73)Tool for defining activities is(73).(73)A.De 计算机类考试 2020-05-26 …

● ()is primarily concerned with defining and conce 计算机类考试 2020-05-26 …

One tool that is useful during both analysis and d 计算机类考试 2020-05-26 …

______is primarily concerned with defining and con 计算机类考试 2020-05-26 …

Tool for defining activities is( ).A.Dependency De 计算机类考试 2020-05-26 …

(75)is primarily concerned with defining and contr 计算机类考试 2020-05-26 …