● A project manager believes that modifying the scope of the project may provide added val

题目

● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).

(75)

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

参考答案
正确答案:B