( )is a project management technique for measuring project performance progress.It has the

题目

( )is a project management technique for measuring project performance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.

A.Critica1 path method(CPM)B.Earned value management(CEV)C.Net present value method(NPVM)D.Expert judgment method(EJM)

参考答案
正确答案:B
看了( )is a project...的网友还看了以下:

● The project life-cycle can be described as(72). 计算机类考试 2020-05-25 …

● You are a project manager for a small project. Y 计算机类考试 2020-05-26 …

The project()is a key input to quality planning si 计算机类考试 2020-05-26 …

( )is a project management technique for measuring 计算机类考试 2020-05-26 …

The project life-cycle can be described as(72). A. 计算机类考试 2020-05-26 …

The project (73) is a key input to quality plannin 计算机类考试 2020-05-26 …

( )is a project management technique for measuring 计算机类考试 2020-05-26 …

In project management , a (1) is a listing of a pr 计算机类考试 2020-05-26 …

You are a project manager for a small project. You 计算机类考试 2020-05-26 …

The project life-cycle can be described as (72).A. 计算机类考试 2020-05-26 …